Building the Anafon Hydro

Following a tendering process in 2014, two contractors were engaged to build the hydro: Gelli Civil Engineering to build the turbine house and the weir and Kevin Williams Earthworks to install the pipeline.

After a village ceremony on 4 May 2015 at which the oldest and youngest residents born in Abergwyngregyn together cut the first turf, Gelli arrived on site on 5 May to commence work on the turbine house. Kevin Williams started work on the pipeline in the Anafon valley on 11 May.

Construction proceeded smoothly in favourable summer weather and both contractors finished work at the end of September 2015.  

However, Scottish Power failed to schedule the work to install their substation in the turbine house and to upgrade the power lines from the village to coincide with the completion of construction of the hydro.  They commenced work on the substation in the middle of October but the work on the power line upgrade did not start until towards the end of that month, by which time the weather had broken, causing further delays.

The upgrade and connection to the grid were eventually completed on 27 November 2015 and work to commission the plant started immediately.   Commissioning was completed on 30 November with the successful completion of the G59 test and the Anafon Hydro commenced full generation and export of electricity to the grid on 1 December, one month earlier than our original target date.